The Hartford Stadium Authority on Tuesday postponed for one week its progress report on Dunkin’ Donuts Park. But Sean Fitzpatrick, executive director of the authority and director of development services for the city, said the worst-case scenario would see an opening day April 13 with the barbecue pit area in left field and an adjacent ramp unavailable until April 19. Read more here.
Tag Archives: Hartford Stadium Authority
Dunkin’ Donuts Progress Report Delayed One Week, But Opening Still Set for April 13
Filed under Design & Construction, Stadium Issues
Dunkin’ Donuts Park Update Today
On Tuesday, with exactly four months left until the Hartford Yard Goats (Double-A, Eastern League) open long-delayed Dunkin’ Donuts Park on April 13, 2017, the Hartford Stadium Authority will hold a monthly meeting to get an update from Arch Insurance, which guaranteed completion of the stadium, and Whiting-Turner Contracting, which took over the job. Read more here.
Filed under Design & Construction, Stadium Issues